Wednesday, December 3, 2008

Lock up


This was the occasion of a the Northlakes Men's Group meeting on the day when the San Remo Community Men's Shed was at lockup for the very first time.

Rob was pointing out some detail of work that would have to be added to the To-Do list ... exciting day for men to gain access to the long awaited shed.

Monday, November 24, 2008

San Remo by night



The San Remo Community Men's Shed is well lit at night and makes a interesting study with the camera during this construction phase.

The Neighbourhood Centre forecourt is well lit from on high and this illuminates not only the trees and parking area it also lights up the Men's Shed. How good will it all look with Christmas Decorations?


The men from Tri-Steel have been a little thwarted by the rainy weather. However, their steady progress means a locked up shed is not far off now.

Like a bush "Cathedral to Carpentry", with "Spires of Steel", the shell of the shed as it now stands looks magnificent among the trees. Industrial aesthetic meets illumination and nature.

Wednesday, November 19, 2008

Inspecting the shed


Tsugio, George, Rob and Jim reviewing progress on the San Remo Community Men's Shed, after having their hearing checked during the group meeting in the Neighbourhood centre.Construction is progressing as fast as possible given the inclement weather.

Tuesday, November 18, 2008

Construction Day


San Remo shedders covered all angles keeping an eye on the construction of the San Remo Community Men's Shed.

George turned up and captured video from early in the morning to any time during the day ... and inside the wire only because it was assembly day not construction zone. Keep out now or the men from Tri-Steel will let you know!!

Kim turned up with big camera to capture some of the action ... soon to appear on the San Remo blog ...Don turned up mid morning to check out the action and see the culmination of work that started from meetings quite some time back now. Finally, seeing the outcome of many meetings, discussions, drawings and financial analysis makes it all worthwhile.


Pity George the First did not make it down today. However, his wife Barbara was eagerly taking photos with her new camera to keep him up to date on progress.

Monday, November 17, 2008

Erection commences


Erection of the San Remo Community Men's Shed commences today, 10 am Monday, 17 November 2008.

Tuesday, September 30, 2008

Slab pour


Work commenced on the San Remo Community Mens Shed. The remnant concrete slab from the pre-school was been cleared by the North Lakes Mens Group. This included slab & brush clearing by Alan Trower and Andy Cox. Trees were felled by the able lumberjacks, George Collie and Richard Huston. Jim Cunningham and George Donaldson while not able to engage in the heavy work have been "supervising" and providing moral support to the team.

Activity Update



Don Flint started off the final preparation on the driveway access to the Mens Shed on friday afternoon assisted by George II and Kim Hopkins.




Meanwhile, Lloyd Amery has been travelling about the Shire assessing and acquiring machines and tools to ensure the operation will be up and running soon after the structure is in place. Even with the lathes and band saws, a grinder and a table saw already donated, there are still plenty of items required for the start up of work within the shed.




Boots the concrete contractor and his team laid out the formwork on Monday morning ready for the concrete pour on Tuesday. Many concrete trucks later and some hard work by his team, saw the slab in finished form by 3pm complete with prepared door entries, some mending to the apron area in front of the shed and additional concrete poured for the driveway access to the side door.




All encircled with a temporary bright orange safety fence, the slab now awaits the arrival of permanent fencing to protect the site while the shed is erected in a few weeks.Exciting to see a new community initiative in the San Remo area!!